Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight



 
 
Thread Tools Display Modes
  #11  
Old October 12th 07, 01:54 AM posted to rec.aviation.piloting
Ron Wanttaja
external usenet poster
 
Posts: 756
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight

On Thu, 11 Oct 2007 22:41:28 GMT, Larry Dighera wrote:

On Thu, 11 Oct 2007 14:27:37 -0700, wrote in
. com:

On Oct 11, 2:23 pm, Larry Dighera wrote:
On Thu, 11 Oct 2007 12:43:43 -0700, wrote in
. com:

None... the whistle blower has nothing to do with it. The delays are
all due to systems integration problems...

What is your source for that information?


Here's one article:

http://www.thenewstribune.com/busine...ry/176438.html

Of course, it could just be a Boeing "cover story."

What do you know about Weldon? His comment to the FAA sounds like he
was unhappy with the lack of regard Boeing showed his engineering
analysis, and when he retired...


"Retired"? Not hardly.

"Weldon was fired in July 2006. He alleged in a whistle-blower complaint with
the U.S. Occupational Safety and Health Administration (OSHA) that the firing
was 'retaliation for raising concerns throughout the last two years of his
employment about the crashworthiness of the 787.'

"But according to a summary of OSHA's findings, Boeing told investigators Weldon
was fired for threatening a supervisor, specifically for stating he wanted to
hang the African-American executive 'on a meat hook' and that he 'wouldn't mind'
seeing a noose around the executive's neck."

http://archives.seattletimes.nwsourc...&date=20070918

Ron Wanttaja

  #12  
Old October 12th 07, 06:11 AM posted to rec.aviation.piloting
[email protected]
external usenet poster
 
Posts: 684
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight

On Oct 11, 4:41 pm, Larry Dighera wrote:
On Thu, 11 Oct 2007 14:27:37 -0700, wrote in
. com:

On Oct 11, 2:23 pm, Larry Dighera wrote:
On Thu, 11 Oct 2007 12:43:43 -0700, wrote in
. com:


None... the whistle blower has nothing to do with it. The delays are
all due to systems integration problems...


What is your source for that information?


Friends (former co-workers) who work on the 787 program at Boeing. I
have known that this was coming for about a year now, so I wasn't at
all surprised by the announcement.


What do you know about Weldon? His comment to the FAA sounds like he
was unhappy with the lack of regard Boeing showed his engineering
analysis, and when he retired, he sold his name and knowledge to Alcoa
marketing. After all, if Boeing re-defines the jetliner as being of
composite construction, aluminum foundries stand to lose a substantial
portion of their market. Is his comment genuine or just underhanded
aluminum industry propaganda?


I don't know anything about Weldon. He worked in a completely
different part of the company (military) than I did (commercial), and
in a different discipline.

Personally, I think that it sounds like he has an axe to grind, and
that he has a different opinion than other experienced engineers at
Boeing. There are too many good engineers there for a bunch of them
to go along with a party line if they felt there was a legitimate
saftey issue.

Dean

  #13  
Old October 12th 07, 01:58 PM posted to rec.aviation.piloting
Montblack
external usenet poster
 
Posts: 972
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight

("Larry Dighera" wrote)
snips
There are a number of points raised in Weldon's comment:

1. The large number of failure modes for the relatively brittle composite
structure used in the 787.

2. The difficulty in testing the composite structure used in the 787.

6. The sensitivity to hot/wet and freeze/thaw conditions an
through-thickness crack growth that represent fatigue-like failure modes
thought to be nonexistent in composites.

7. Visually undetectable impact caused micro-cracking as might occur with
hail damage.



Sounds like just what the Dr. ordered...

From yesterday's e-Hotline
(EAA eHotline Volume 7 Number 49)

NANOTUBES DETECT, REPAIR WING DAMAGE
"Adding even a small amount of carbon "nanotubes" can go a long way toward
enhancing the strength, integrity, and safety of composite structures,
according to a new study at Rensselaer Polytechnic Institute, New York.
Researchers there have developed a simple new technique for identifying and
repairing small, potentially dangerous cracks in high-performance aircraft
wings and many other composite structures. By infusing the polymer with
electrically conductive carbon nanotubes and monitoring the electrical
resistance at different points in the structure, Professor Nikhil Koratkar,
who developed the method, can pinpoint the location and length of even the
tiniest stress-induced crack."

A more detailed story from Science Daily: Oct 4, 2007

http://www.sciencedaily.com/releases/2007/09/070927132550.htm
The majority of failures in any engineered structure are generally due to
fatigue-induced microcracks that spread to dangerous proportions and
eventually jeopardize the structure's integrity, Koratkar said. His research
is looking to solve this problem with an elegant solution that allows for
real-time diagnostics and no additional or expensive equipment.

Koratkar's team made a structure from common epoxy, the kind used to make
everything from the lightweight frames of fighter jet wings to countless
devices and components used in manufacturing and industry, but added enough
multi-walled carbon nanotubes to comprise 1 percent of the structure's total
weight. The team mechanically mixed the liquid epoxy to ensure the carbon
nanotubes were properly dispersed throughout the structure as it dried in a
mold.

The researchers also introduced into the structure a series of wires in the
form of a grid, which can be used to measure electrical resistance and also
apply control voltages to the structure.

By sending a small amount of electricity through the carbon nanotubes, the
research team was able to measure the electrical resistance between any two
points on the wire grid. They then created a tiny crack in the structure,
and measured the electrical resistance between the two nearest grid points.
Because the electrical current now had to travel around the crack to get
from one point to another, the electrical resistance - the difficulty
electricity faces when moving from one place to the next - increased. The
longer the crack grew, the higher the electrical resistance between the two
points increased.

Plus, Koratkar's system features a built-in repair kit.

When a crack is detected, Koratkar can increase the voltage going through
the carbon nanotubes at a particular point in the grid. This extra voltage
creates heat, which in turn melts a commercially available healing agent
that was mixed into the epoxy. The melted healing agent flows into the crack
and cools down, effectively curing the crack. Koratkar shows that these
mended structures are about 70 percent as strong as the original, uncracked
structure - strong enough to prevent a complete, or catastrophic, structural
failure. This method is an effective way to combat both microcracks, as well
as a less-common form of structural damage called delamination.

"What's novel about this application is that we're using carbon nanotubes
not just to detect the crack, but also to heal the crack," he said. "We use
the nanotubes to create localized heat, which melts the healing agent, and
that's what cures the crack."


Montblack
https://secure.eaa.org/ehotline/subscribe.html


  #14  
Old October 12th 07, 02:38 PM posted to rec.aviation.piloting
Montblack
external usenet poster
 
Posts: 972
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight

("Ron Wanttaja" wrote)
"But according to a summary of OSHA's findings, Boeing told investigators
Weldon was fired for threatening a supervisor, specifically for stating he
wanted to hang the African-American executive 'on a meat hook' and that he
'wouldn't mind' seeing a noose around the executive's neck."



Brings immediately to mind (4) movies:

1. On the Waterfront (1953)
2. The Ox-Bow Incident (1943)

NAC (Necessary Aviation Content) movies:

1. Goodfellas (1990) ...post Lufthansa/JFK-heist freezer scene

2. Airplane! (1980)
Hanging Lady: "Nervous?"
Ted Striker: "Yes."
Hanging Lady: "First time?"
Ted Striker: "No, I've been nervous lots of times."


Montblack!
"So there."


  #16  
Old October 20th 07, 06:08 PM posted to rec.aviation.piloting
[email protected]
external usenet poster
 
Posts: 183
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight

On Oct 10, 10:18 pm, Kingfish wrote:
On Oct 10, 9:01 pm, Larry Dighera wrote:

One wonders how much the setbacks in Boeing's 787 program are a result
of the whistle-blowing former Boeing engineer's comments to the FAA
citing shortcuts and unsound engineering decisions for the 787. Here's
the link to the document:http://seattletimes.nwsource.com/ABP...2003889769.pdf


Regardless of the alleged whistle blowing, program delays don't
surprise me considering the complexity of 787.


They need Revell or Monogram to fix the plastic airframe issues, until
then I'm sticking with Airbus..JG

  #17  
Old April 9th 08, 04:01 PM posted to rec.aviation.piloting
Larry Dighera
external usenet poster
 
Posts: 3,953
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight

The Boeing Company http://www.boeing.com/news/releases/index.html
Boeing Revises 787 First Flight and Delivery Plans; Adds Schedule
Margin to Reduce Risk of Further Delays

* First flight moved into fourth-quarter 2008; deliveries to
begin third-quarter 2009

* Production plan now targets approximately 25 787 deliveries in
2009

* Company expresses confidence in plans; will work closely with
customers to minimize disruption

* No change to 2008 earnings guidance; strong 2009 EPS growth
still expected

EVERETT, Wash., April 09, 2008 -- Boeing [NYSE: BA] today announced a
revised plan for first flight and initial deliveries of the 787
Dreamliner that includes additional schedule margin to reduce risk of
further delays on the program.

While significant progress has been made assembling Airplane #1, first
flight is being rescheduled due to slower than expected completion of
work that traveled from supplier facilities into Boeing's final
assembly line, unanticipated rework, and the addition of margin into
the testing schedule. The new delivery schedule is based on a more
conservative production plan developed with the 787 partner team. That
schedule now targets approximately 25 deliveries in 2009.

First flight of the all-new airplane will move into the fourth quarter
of this year rather than the end of the second quarter, and first
delivery is now planned for the third quarter of 2009 instead of first
quarter.

Company officials expressed confidence in the new plan and the steps
being taken to accelerate program performance.

"Over the past few months, we have taken strong actions to confront
and overcome start-up issues on the program, and we have made solid
progress," said Boeing Commercial Airplanes President and CEO Scott
Carson. "Nevertheless, the traveled work situation and some
unanticipated rework have prevented us from hitting the milestones we
laid out in January. Our revised schedule is built upon an achievable,
high-confidence plan for getting us to our power-on and first-flight
milestones. Also, while the fundamental technologies and design of the
787 remain sound, we have inserted some additional schedule margin for
dealing with other issues we may uncover in testing prior to first
flight and in the flight test program."

The company said in January it would be conducting a comprehensive
assessment of its supply chain and production system capabilities to
determine the details of the 787's flight test program and initial
delivery profile. As a result of that assessment, the first-year
delivery plan announced today will be followed by a more gradual ramp
up to full-rate production than previously planned.

"We deeply regret the disruption and disappointment these changes will
cause for our customers, and we will work closely with each of them to
minimize the impact," said Carson. "We have taken significant action
to improve supply chain and production system performance, such as our
investment in Global Aeronautica, but based on our assessment, the
prudent course is to proceed with a more gradual ramp up to full-rate
production."

Pat Shanahan, 787 vice president and program manager, echoed Carson's
comments about the progress being made in 787 factories.

"The work that remains to be done on Airplane #1 is well defined, and
we can see our way to -- and have confidence in -- the new mil estones
we have set for it," said Shanahan. "We have addressed the major
challenges that slowed our progress while trying to complete the
primary structure -- the parts shortages, engineering changes, and
manufacturing changes -- and we are well into the systems installation
that is the precursor to putting power on the airplane for the first
time. We have also worked closely with our partners to achieve higher
levels of completion of their parts of subsequent airplanes, and we
will continue to drive improvements in the supply chain and production
system performance," he said.

For tracking program progress, Shanahan outlined a series of
milestones that will occur before June 30: 787 static and fatigue
structural test airplanes will move to their testing locations;
Airplanes #3 and #4 will enter final assembly; hardware airworthiness
qualifications will be complete; and power on will be achieved.

Shanahan also said the program has changed the timing of the
introduction of two 787 derivatives. The 787-9, a larger variant of
the airplane, will be the first derivative of the baseline 787 with
delivery planned for early 2012. The 787-3, a shorter-range model
previously slated to deliver in 2010, will now become the second
derivative of the airplane family.

While research and development costs will likely increase as a result
of the 787 schedule change, Boeing expects no change to 2008 earnings
guidance. The company continues to expect strong earnings per share
growth in 2009 and will provide complete 2009 financial guidance when
it holds its first-quarter 2008 earnings conference call later this
month. The outlook for the company's defense business and
in-production commercial airplane programs remains strong.

Boeing will hold a conference call
http://phx.corporate-ir.net/playerlink.zhtml?c=85482&s=wm&e=1814923
with Scott Carson and Pat Shanahan to discuss the 787 program today at
11:00 a.m. EDT, 8:00 a.m., PDT.


  #18  
Old April 9th 08, 07:13 PM posted to rec.aviation.piloting
[email protected]
external usenet poster
 
Posts: 684
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and FirstFlight

Boeing press release snipped

Personally, I think that this is the right move to make if there is a
design problem with the wing box. That is the most critical
structural area on the airplane, and an in-flight failure of the wing
box would be a complete disaster. This is the first all-composite
commercial airliner ever designed and built. It absolutely needs to
be done right.

I'm sure that the structural engineers took their best shot at the
initial design, but then realized after testing the initial units that
were produced that something was inadequate and needed to be fixed.
If engineering was easy and could be done without a degree of trial
and error, anybody with a high school diploma could do it!

On a development program like this, every group is racing to get their
stuff done on time, and at the very least ahead of the slowest group.
You never want to be the part of the effort that causes the delay,
it's not fun! It's like the old joke about hikers running from a
grizzly bear. They can't outrun the bear, but they only need to
outrun the slowest hiker...

Fortunately on the 777, we managed to pull everything together on
time. The 787 is more challenging than the 777 for a number of
reasons, and unfortunately they are behind schedule. I guarantee that
there will be a "lessons learned" document that come out after this
project that is pretty hefty.

Dean
  #19  
Old April 9th 08, 08:31 PM posted to rec.aviation.piloting
Larry Dighera
external usenet poster
 
Posts: 3,953
Default Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight

On Wed, 9 Apr 2008 11:13:13 -0700 (PDT), wrote:

This is the first all-composite
commercial airliner ever designed and built. It absolutely needs to
be done right.



I couldn't agree more.

Thank you for sharing your insight on the issue.
  #20  
Old June 21st 08, 09:11 PM posted to rec.aviation.piloting
Larry Dighera
external usenet poster
 
Posts: 3,953
Default 787 Dreamliner Power On Sequence Underway (Was: Boeing Reschedules Initial 787 Dreamliner Deliveries and First Flight)




http://www.newairplane.com/787/en-US...eves787PowerOn
Everett, Washington, June 20, 2008
Boeing Achieves 787 Power On

The Boeing Company has completed the Power On sequence for the
first 787 Dreamliner, marking the completion of the next major
milestone on the path to first flight later this year.

Power On is a complex series of tasks and tests that bring
electrical power into the airplane and begin to exercise the use
of the electrical systems. The 787 is a more-electric airplane
with the pneumatic, or bleed air, system being totally replaced by
electronics.

"The team has made great progress in bringing the bold innovation
of the 787 to reality," said Pat Shanahan, vice president and
general manager of the 787 program. "There is plenty of work to
be done between now and the first flight, but with every step
forward we grow more and more confident."

The power On sequence began in early June with a series of pretest
continuity checks to verify that the wiring installed in the
airplane had been connected properly. Upon completion of those
checks, the Boeing team plugged in an external power cart and
slowly began to bring full power into each segment of the system,
beginning with the flight deck displays. From that point forward,
the pilot's controls were used to direct the addition of new
systems to the power grid.

At each step of the testing, power is allowed to flow into one
additional area and gauges are used to verify that the right level
of electrical power is reached the intended area. "We are very
methodical in ensuring the integrity of the airplane's systems,"
said Shanahan. "In completing the Power On sequence, we have
verified both that the electrical power distribution system is
installed as designed and that it functions as intended."

An inside look at the Power On testing sequence will be featured
on www.boeing.com and newairplane.com beginning Monday at 5 a.m.
PDT.

 




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Dreamliner out Sunday Jim Morris[_2_] Aviation Photos 2 July 9th 07 05:24 AM
Dreamliner goes out the door. shiver Aviation Photos 2 July 7th 07 05:01 PM
787 Dreamliner Photos RL Anderson Piloting 10 June 29th 07 06:21 PM
Dreamliner Nears Production Jay Beckman Piloting 22 December 6th 06 04:15 AM
SC Dreamliner Factory john smith Piloting 2 June 9th 06 06:41 PM


All times are GMT +1. The time now is 06:27 AM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 AviationBanter.
The comments are property of their posters.